Shanan power project: Himachal vs Punjab

Shanan power project explained for UPSC aspirants
Map showing the Shanan power project at Joginder Nagar in Himachal Pradesh.
Shanan: the lease and its legacy
The issue in 30 seconds

The 110 MW Shanan hydropower project at Joginder Nagar, Mandi, is disputed by Himachal Pradesh and Punjab. Its 99-year lease expired in March 2024, after which Himachal claimed the project. Punjab filed a Supreme Court suit asserting ownership and lawful possession. The Court decided to hear Himachal’s objection to the suit’s maintainability first. A 2025 report said the impasse had halted essential maintenance and investment.

Exam angles
HPAS Mains: federal disputesHPRCA: Himachal GKArticle 131Hydropower governancePunjab Reorganisation Act

Timeline: the lease and the dispute

  1. 1925lease
    Agreement

    Mandi’s Raja Joginder Sen and British officer B.C. Batty agreed to a 99-year lease.

  2. 1966reorganisation
    Transfer

    The project went to Punjab under the Punjab Reorganisation Act 1966.

  3. March2024
    Expiry

    The lease expired; Himachal claimed the 110 MW project.

  4. Late 2024court
    Maintainability

    The Supreme Court said it would first hear Himachal’s objection to Punjab’s suit.

  5. 2025maintenance
    Impasse

    A report said the ownership dispute had halted essential maintenance and investment.

Remember1925 · 1966 · 2024 — lease, reorganisation, expiry.
HP exam one-liners
  • Shanan is a 110 MW hydropower project.
  • It is located at Joginder Nagar in Mandi district.
  • The project uses water from the Uhl, a Beas tributary.
  • The 99-year lease expired in March 2024.
  • Punjab brought its original suit under Article 131 of the Constitution.

What is the Shanan dispute?

Shanan was built under a 1925 lease between Raja Joginder Sen of Mandi and the British, represented by Colonel B.C. Batty. It was among north India’s first major hydel projects and used Uhl water to supply undivided Punjab, Lahore and Delhi. The project went to Punjab under the Punjab Reorganisation Act 1966.

After the lease expired, Himachal claimed the project should pass to it. Punjab asserted ownership and lawful possession in its Supreme Court suit. Himachal objected to the suit’s maintainability, citing the Article 131 proviso concerning certain pre-Constitution agreements; Haryana sought to be heard.

Why it matters

For local communities

Project maintenance and safe operation matter to people living near the facility in Joginder Nagar.

For hydropower assets

The reported halt in essential maintenance and investment affects the upkeep of a 110 MW generating asset.

For federal governance

The dispute concerns inter-state claims and the Supreme Court’s original jurisdiction. The Union Power Ministry asked both states to maintain status quo.

Himachal GK connect
  • District: Joginder Nagar is in Mandi district.
  • River: The Uhl is a tributary of the Beas.
  • Railway: The Kangra Valley Railway was built partly to carry material for the project.

Key data

PointDetails
Capacity and location110 MW; Joginder Nagar, Mandi
RiverUhl, a Beas tributary
Lease99 years; agreement in 1925; expired in March 2024
ReorganisationProject went to Punjab under the Punjab Reorganisation Act 1966
Constitutional provisionArticle 131: original jurisdiction in specified disputes involving states and the Union
Legal questionHimachal contests maintainability of Punjab’s suit under the Article 131 proviso
Operational concernEssential maintenance and investment reportedly halted amid the dispute in 2025

Way forward

  • Protect safety: Coordinate essential inspections and maintenance while respecting the status quo and court directions.
  • Share information: Maintain a joint technical record of equipment condition, risks and urgent repairs.
  • Support adjudication: Place relevant lease, reorganisation and operational records before the Court.
  • Consult communities: Communicate safety measures and emergency arrangements to residents and workers.
  • Safeguard the river: Assess maintenance work for impacts on the Uhl and the fragile Himalayan environment.

HPAS Mains practice questions

Explain the origins and main claims in the Shanan power project dispute. (150 words)

Answer pointers:

  • Introduce the 1925 lease and the project’s location.
  • Note the 1966 reorganisation and March 2024 expiry.
  • Set out Punjab’s claim and Himachal’s objection.
  • Conclude with the need for lawful resolution and asset safety.
Critically examine the governance challenges posed by the Shanan dispute. (250 words)

Answer pointers:

  • Introduce the disputed project and its federal setting.
  • Discuss judicial adjudication and status quo as means of managing competing claims.
  • Examine reported maintenance delays, investment concerns and local safety.
  • Conclude with coordinated upkeep and respect for court directions.
As SDM of Joginder Nagar, how would you address local safety concerns around Shanan during the dispute? (150 words)

Answer pointers:

  • Identify the dispute and the need to maintain public safety.
  • Coordinate inspections with the project operator and competent technical authorities.
  • Prepare emergency communication and consult nearby communities.
  • Report risks promptly while respecting legal and administrative directions.
Discuss the relevance of Article 131 to inter-state disputes, with reference to Shanan. (150 words)

Answer pointers:

  • Introduce the Supreme Court’s original jurisdiction under Article 131.
  • Explain Punjab’s suit and the competing state claims.
  • Note Himachal’s maintainability objection based on the proviso.
  • Conclude that the Court must determine the legal questions.
Exam tip

For Himachal Pradesh Administrative Service (HPAS) prelims and Himachal Pradesh Rajya Chayan Aayog (HPRCA) recruitment papers, memorise the location, river, capacity and lease dates. For HPAS Mains, connect the claims to Article 131 and maintenance concerns.

Preparing for HPAS or an HPRCA exam? Practise topics like this with CBL’s HPAS batch.See the course →

MCQ Practice Corner

Q1. Consider the following statements about the Shanan project:
1. It uses water from the Uhl river.
2. Its 99-year lease expired in March 2024.
3. It is located in Kinnaur district.
Which statements are correct?

(a) 1 and 2 only  (b) 2 and 3 only  (c) 1 and 3 only  (d) 1, 2 and 3

Show answer

Answer: (a) because Shanan is in Mandi, not Kinnaur.

Q2. Punjab filed its original suit over Shanan under which constitutional provision?

(a) Article 131  (b) Article 275  (c) Article 356  (d) Article 368

Show answer

Answer: (a) because Article 131 concerns the Supreme Court’s original jurisdiction in specified disputes.

Q3. What is the capacity of the Shanan hydropower project?

(a) 99 MW  (b) 110 MW  (c) 192 MW  (d) 275 MW

Show answer

Answer: (b) because Shanan has a capacity of 110 MW.

Q4. Shanan is located at which place?

(a) Joginder Nagar  (b) Reckong Peo  (c) Chamba  (d) Nahan

Show answer

Answer: (a) because the project is at Joginder Nagar in Mandi district.

Frequently Asked Questions

Where is the Shanan power project located?

It is at Joginder Nagar in Mandi district, Himachal Pradesh. The project uses water from the Uhl river.

When did the Shanan project lease expire?

The 99-year lease expired in March 2024. The lease agreement was made in 1925.

Why are Himachal Pradesh and Punjab disputing Shanan?

Himachal claims the project should pass to it after the lease expiry, while Punjab asserts ownership and lawful possession. Himachal has also challenged the maintainability of Punjab’s Supreme Court suit.

Sources: ETV Bharat, The Week (PTI), The Tribune: maintenance, The Tribune: maintainability

Preparing for UPSC, PCS or HCS?

Talk to a mentor at Chetan Bharat Learning, Chandigarh. Free guidance on choosing the right exam and building a study plan.

Chat on WhatsAppCall 97793 53345

UPSC / IAS / PCS coaching in Chandigarh · Trusted by aspirants across Punjab & Haryana

No comments to show.

Leave a Reply

Chetan Bharat Learning
Chetan Bharat LearningUPSC · PCS · HCS coaching, Chandigarh
Call / WhatsApp 97793-53345 · currentaffairs.chetanbharat.com
Prepared by Chetan Bharat Learning
New UPSC batches: 7 & 21 December · Classroom, Live Online & Recorded
Call / WhatsApp 97793-53345 · ISBT 43, First Floor, Sector 43, Chandigarh
Source: https://currentaffairs.chetanbharat.com/shanan-power-project-himachal-current-affairs/
Book free session WhatsApp